Prüfung C_TSCM62_65

Prüfung C_TSCM62_65 SAP Certified Application Associate – Order Fulfillment with SAP ERP 6.0 EHP5 www.it-pruefungen.de

QUESTION NO: 1
Which of the following elements can directly influence whether an availability check will be
performed? (Choose two)

A. The schedule line category in the sales document
B. The delivery type
C. The check group in the material master
D. The item category in the sales document

Answer: A,C

QUESTION NO: 2
Based on which of the following dates is the availability check (ATP) carried out?

A. Requested delivery date
B. Replenishment lead date
C. Material availability date
D. Goods issue date

Answer: C

C_TSCM62_65 Prüfungsvorbereitung Studienmaterial deutsch SAP Certified Application Associate – Order Fulfillment with SAP ERP 6.0 EHP5 https://www.it-pruefungen.de/C_TSCM62_65.htm

QUESTION NO: 3
According to the system there is no stock available, but you still receive a confirmed schedule line in the sales order.
What is the reason for this confirmation?

A. The availability check that was carried out included a replenishment lead time in the scope of check.
B. The system automatically searches other plants for inventory and transfers this inventory to the plant with zero inventory in the sales order.
C. The availability check was carried out, and on saving, the system immediately rescheduled the sales order according to the customer priority.
D. Inventory Management creates a stock transfer when the sales order is saved.

Answer: A

QUESTION NO: 4
If the material entered in the sales order is not available, how is the user alerted to this situation?

A. The incompletion log displays the unconfirmed schedule line as a missing field.
B. The availability control screen is displayed.
C. The schedule line is marked and highlighted by the system.
D. An error message appears on the status bar alerting the user to the situation.

Answer: B

C_TSCM62_65 Prüfungsfragen SAP Certified Application Associate – Order Fulfillment with SAP ERP 6.0 EHP5 www.it-pruefungen.de

QUESTION NO: 5
As a member of the project team, you are asked to set up the system so that user has to enter an order reason when processing a sales order. It should be possible to save the incomplete order, but further processing should not be possible until the Order Reason field is filled.
How do you implement this requirement?

A. You define an incompletion procedure with the Order Reason field and mark it as mandatory.
B. You define an incompletion procedure with the Order Reason field and assign a status group in which the fields General, Delivery, and Billing Document are selected.
C. You define an incompletion procedure with the Order Reason field, assign it to the sales document type, and set the status to “released for further process steps”.
D. You define an incompletion procedure with the Order Reason field and assign it to a sales document type that has the “Incompletion Message” indicator set.

Answer: B