C_TSCM42_65 Prüfungsfragen

www.it-pruefungen.de C_TSCM42_65 Prüfungsfragen, C_TSCM42_65 Examensfragen SAP Certified Application Associate – Production – Planning & Manufacturing with SAP ERP 6.0 EHP5 (ICND2 v3.0)

QUESTION NO: 1
What features related to process orders can be used to fulfill Good Manufacturing Practices (GMP) requirements? (Choose three)

A. Availability check
B. Digital signature
C. Resource selection
D. Electronic batch record
E. Approved master recipes

Answer: B,D,E

QUESTION NO: 2
Which of the following statements about consumption are correct? (Choose two)

A. Consumption takes place on the material level between the planned independent requirements and the planned orders.
B. Consumption parameters (consumption mode and consumption interval) can be set in the material master or in the MRP group.
C. Consumption is restructured with the planning run.
D. Consumption can take place between order reservations and planned independent
requirements, depending on the strategy.

Answer: B,D

QUESTION NO: 3
Where can you define the valid receivers for production order costs?

A. In the valuation variant
B. In the production scheduling profile
C. In the settlement profile
D. In the costing variant

Answer: C

Prüfungsvorbereitung C_TSCM42_65 Studienmaterial deutsch SAP Certified Application Associate – Production – Planning & Manufacturing with SAP ERP 6.0 EHP5  https://www.it-pruefungen.de/C_TSCM42_65.htm

QUESTION NO: 4
When analyzing the SAP ECC order report for a planned order for a finished product, you discover that one of the assemblies will not be available in time for the scheduled final assembly because of automatic forward scheduling.
Which planning procedure do you use to create a feasible production plan from a requirements planning perspective?

A. Interactive single-item planning for the delayed assembly
B. Multi-level single-item planning with the “simulation mode” option
C. Total planning online
D. Multi-level single-item planning with the “display material list” option

Answer: B

QUESTION NO: 5
What does SAP ERP mean?

A. SAP ERP is a planning system in which extended planning processes can be mapped.
B. SAP ERP is a system hardware that includes modules for purchasing, sales and distribution, materials management, production and so on.
C. SAP ERP is a technological platform, on the basis of which customer-specific extensions can be imported.
D. SAP ERP is an application that an enterprise can use to manage its business processes efficiently.

Answer: D

IT-Prüfungen C_TSCM42_65 SAP Certified Application Associate – Production – Planning & Manufacturing with SAP ERP 6.0 EHP5 www.it-pruefungen.de

QUESTION NO: 6
Which functions can be triggered before releasing a production order? (Choose three)

A. Confirmation
B. Selection of a routing
C. Scheduling
D. Stock determination
E. Selection of a BOM

Answer: B,C,E

C_TSCM42_66 Prüfung, C_TSCM42_66 zertifizierung

www.it-pruefungen.de sap C_TSCM42_66 Prüfung, C_TSCM42_66 zertifizierung Production – Planning & Manufacturing with SAP ERP 6.0 EHP6

QUESTION NO: 1

You want to use the function “Read PP master data” in the production order.

However, while calling the function you receive an error message.

What could be the reason?

A. The material availability check has been performed.
B. Goods movements have been posted.
C. The production order has been released.
D. Order papers have been printed.

Answer: B

QUESTION NO: 2

Which objects can affect the calculation of capacity requirements for an operation? (Choose three)

A. Standard values (routing)
B. In-house production time (material master)
C. Transport time (routing)
D. Formulas (work center)
E. Operation control key (routing)

Answer: A,D,E

QUESTION NO: 3

In the Customizing for requirements planning, a project team notices that the alternatives P1, P2, P3 and P4 are also delivered as standard in addition to MRP type PD. The number in each of these alternatives represents a firming type.

What does a firming type define? (Choose two)

A. Handling existing procurement proposals outside the planning time fence.
B. Handling existing procurement proposals within a planning time fence.
C. Handling new requirements within the planning time fence.
D. Handling new procurement proposals that need to be created due to new requirements within the planning time fence.

Answer: B,D

sap C_TSCM42_66 Prüfungsfragen, sap C_TSCM42_66 Examensfragen Production – Planning & Manufacturing with SAP ERP 6.0 EHP6 (ICND2 v3.0) www.it-pruefungen.de

QUESTION NO: 4

Which of the following scheduling types can only be used in capacity planning?

A. Midpoint
B. Forward
C. Only capacity requirements
D. Backward

Answer: A

QUESTION NO: 5

Which types of objects can be changed with Engineering Change Management (ECM)? (Choose three)

A. Task list
B. Work center
C. Production version
D. Bill of material
E. Material master

Answer: A,D,E

C_TSCM42_66 Prüfungsvorbereitung Studienmaterial sap deutsch Production – Planning & Manufacturing with SAP ERP 6.0 EHP6 www.it-pruefungen.de

QUESTION NO: 6

Which of the following master data can be used with process orders? (Choose three)

A. Serial numbers
B. Master recipes
C. Resources
D. Production/resource tools
E. Production versions

Answer: B,C,E

Prüfung C_TSCM52_66

Prüfung C_TSCM52_66 SAP Certified Application Associate – Procurement with SAP ERP 6.0 EHP6

QUESTION NO: 1
You have received an order confirmation from a vendor.
What do you have to do before you can enter the confirmed delivery date and confirmed quantity in a purchase order item?

A. Set the Goods Receipt indicator.
B. Set the Confirmation Received indicator in the header.
C. Use a confirmation control key in the relevant purchase order item.
D. Set the Acknowledgement Required indicator in the vendor master of the relevant vendor.

Answer: C

QUESTION NO: 2
Where do you define a fixed vendor for a specific period in time?

A. In the info record at client level (regular vendor)
B. In the quota arrangement at plant level
C. In the source list at plant level
D. In the material master at plant level

Answer: C

QUESTION NO: 3
What are characteristics of material valuation at the moving average price? (Choose two)

A. If you book a subsequent debit for a quantity higher than the total quantity of valuated stock then a price difference posting is generated.
B. If the price in the purchase order is different from the moving average price then a price
difference posting is generated at goods receipt.
C. The moving average price is equal to the total value divided by total quantity of valuated stock.
D. Goods movements are always valuated based on the moving average price from the material master record.

Answer: A,C

C_TSCM52_66 Prüfungsvorbereitung, C_TSCM52_66 Studienmaterialien deutsch SAP Certified Application Associate – Procurement with SAP ERP 6.0 EHP6  https://www.it-pruefungen.de/C_TSCM52_66.htm

QUESTION NO: 4
Which value of the creation indicator is shown in the tab Contact person when you create a purchase requisition manually?

A. Production Order
B. Direct procurement
C. Realtime
D. Material requirements planning

Answer: C

C_TSCM52_66 Prüfungsfragen SAP Certified Application Associate – Procurement with SAP ERP 6.0 EHP6 www.it-pruefungen.de

QUESTION NO: 5
What does an account group control when you create vendor master records? (Choose three)

A. The partner determination procedure
B. The definition whether the vendor master record is a one-time account or not
C. The possible data retention levels
D. The reconciliation account in general ledger
E. The possible payment terms

Answer: A,B,C

C_TSCM52_67 Prüfungsvorbereitung

C_TSCM52_67 Prüfungsvorbereitung deutsch SAP Certified Application Associate – Procurement with SAP ERP 6.0 EhP www.it-pruefungen.de

QUESTION: 1

Deliveries often arrive too late. You therefore want to send reminders to your vendors.

Which prerequisites must be fulfilled to generate reminders for a purchase order item? (Choose two)

A. The delivery date is at least one week in the past.
B. You have entered at least one reminder level in the purchase order item.
C. The purchase order must be output.
D. The purchase order item has no account assignment category.

Answer: B,C

QUESTION: 2

What information can you specify in a quota arrangement? (Choose two)

A. An outline agreement number for external procurement requirements
B. An info record number for external procurement requirements
C. A procurement type for each source
D. A quota you want to assign to the source

Answer: C,D

sap C_TSCM52_67 Prüfungsfragen, C_TSCM52_67 Examensfragen SAP Certified Application Associate – Procurement with SAP ERP 6.0 EhP (ICND2 v3.0) www.it-pruefungen.de

QUESTION: 3

What can you specify when you assign a message schema to an application in Purchasing?

A. The number of outputs for print messages
B. The permitted output media, for example print output or fax
C. That a new message determination process is initiated for change messages
D. The access sequence for the message types

Answer: C

QUESTION: 4

When you use the collective release, which indicators do you have to set to select all purchase requisitions that you can release if you do not know if the purchase requisitions require overall release or per item release?(Choose three)

A. Requisitions for overall release
B. Sort indicator 1
C. Blocking indicator 1
D. Requisitions for item wise release
E. Release prerequisite fulfilled

Answer: A,D,E

IT-Prüfungen C_TSCM52_67 SAP Certified Application Associate – Procurement with SAP ERP 6.0 EhP www.it-pruefungen.de

QUESTION: 5

Which of the following are characteristics of a service purchase order? (Choose three)

A. Service specifications are required.
B. A limit value for unplanned services can be specified.
C. An account assignment is mandatory.
D. A service master number is required.
E. The item category is D (service).

Answer: B,C,E

C_TSCM62_64 Prüfung, C_TSCM62_64 zertifizierung

C_TSCM62_64 Prüfung, C_TSCM62_64 zertifizierung SAP Certified Application Associate – Order Fulfillment with SAP ERP 6.0 EHP4 www.it-pruefungen.de

QUESTION NO: 1
The availability check (ATP) is carried out based on which of the following dates?

A. The material availability date
B. The transportation planning date
C. The goods issue date
D. The loading date

Answer: A

QUESTION NO: 2
In the system, it is possible to have zero stock available and still receive a confirmed schedule line in the sales order. Which of the following states the reason for this confirmation?

A. Stock will be taken from another delivery at the shipping point.
B. The system automatically searches other plants for inventory and transfers this inventory to the plant with zero inventory in the sales order.
C. The availability check that was carried out included a replenishment lead time in the scope of check.
D. A stock transfer will be created by inventory management when you save the sales order.

Answer: C

C_TSCM62_64 Prüfungsfragen, C_TSCM62_64 Examensfragen SAP Certified Application Associate – Order Fulfillment with SAP ERP 6.0 EHP4 (ICND2 v3.0)  https://www.it-pruefungen.de/C_TSCM62_64.htm

QUESTION NO: 3
During sales order processing, a user will be alerted when stock is not available for material entered in the sales order if the availability check was carried out. In which of the following ways will the user be alerted about this situation?

A. An error message will appear on the status bar alerting the user to the situation.
B. The schedule line will be marked and highlighted by the system.
C. The availability control screen will be displayed.
D. The incompletion log will display the unconfirmed schedule line as a missing field.

Answer: C

QUESTION NO: 4
Which of the following elements can directly influence whether an availability check will be
performed? Note: There are 3 correct answers to this question.

A. The schedule line category in the sales document
B. The item category in the delivery document
C. The check group in the material master
D. The item category in the sales document
E. The sales document type

Answer: A,B,C

C_TSCM62_64 Prüfungsvorbereitung Braindump deutsch SAP Certified Application Associate – Order Fulfillment with SAP ERP 6.0 EHP4 www.it-pruefungen.de

Prüfung C_TSCM62_65

Prüfung C_TSCM62_65 SAP Certified Application Associate – Order Fulfillment with SAP ERP 6.0 EHP5 www.it-pruefungen.de

QUESTION NO: 1
Which of the following elements can directly influence whether an availability check will be
performed? (Choose two)

A. The schedule line category in the sales document
B. The delivery type
C. The check group in the material master
D. The item category in the sales document

Answer: A,C

QUESTION NO: 2
Based on which of the following dates is the availability check (ATP) carried out?

A. Requested delivery date
B. Replenishment lead date
C. Material availability date
D. Goods issue date

Answer: C

C_TSCM62_65 Prüfungsvorbereitung Studienmaterial deutsch SAP Certified Application Associate – Order Fulfillment with SAP ERP 6.0 EHP5 https://www.it-pruefungen.de/C_TSCM62_65.htm

QUESTION NO: 3
According to the system there is no stock available, but you still receive a confirmed schedule line in the sales order.
What is the reason for this confirmation?

A. The availability check that was carried out included a replenishment lead time in the scope of check.
B. The system automatically searches other plants for inventory and transfers this inventory to the plant with zero inventory in the sales order.
C. The availability check was carried out, and on saving, the system immediately rescheduled the sales order according to the customer priority.
D. Inventory Management creates a stock transfer when the sales order is saved.

Answer: A

QUESTION NO: 4
If the material entered in the sales order is not available, how is the user alerted to this situation?

A. The incompletion log displays the unconfirmed schedule line as a missing field.
B. The availability control screen is displayed.
C. The schedule line is marked and highlighted by the system.
D. An error message appears on the status bar alerting the user to the situation.

Answer: B

C_TSCM62_65 Prüfungsfragen SAP Certified Application Associate – Order Fulfillment with SAP ERP 6.0 EHP5 www.it-pruefungen.de

QUESTION NO: 5
As a member of the project team, you are asked to set up the system so that user has to enter an order reason when processing a sales order. It should be possible to save the incomplete order, but further processing should not be possible until the Order Reason field is filled.
How do you implement this requirement?

A. You define an incompletion procedure with the Order Reason field and mark it as mandatory.
B. You define an incompletion procedure with the Order Reason field and assign a status group in which the fields General, Delivery, and Billing Document are selected.
C. You define an incompletion procedure with the Order Reason field, assign it to the sales document type, and set the status to “released for further process steps”.
D. You define an incompletion procedure with the Order Reason field and assign it to a sales document type that has the “Incompletion Message” indicator set.

Answer: B

Prüfungsvorbereitung auf C_TSCM62_66 PDF

Prüfungsvorbereitung auf C_TSCM62_66 PDF Studienmaterial deutsch SAP Certified Application Associate – Sales and Distribution, ERP 6.0 EhP6 www.it-pruefungen.de

QUESTION: 1

Which statement regarding copying control is correct?

A. The copying requirements for sales documents can be specified at header and item level only.
B. Copying control allows you to create sales documents with reference to other sales documents, delivery documents, and billing documents.
C. The item category of the target document must always be specified in copying control.
D. Copying control for sales documents controls the transfer of data at header, item, and schedule-line level.

Answer: D

QUESTION: 2

You are using rental contracts.

Which setting is mandatory for working with periodic billing?

A. Assignment of the service billing document type FS (Invoice Service/Rent) to the item category of the rental contract item.
B. Maintenance of a separate billing type that is assigned to the sales document type of the rental contract
C. Maintenance of a factory calendar that is assigned to the customer master
D. Assignment of an appropriate billing plan type to the item category of the rental contract item

Answer: D

IT-Prüfungen C_TSCM62_66 SAP Certified Application Associate – Sales and Distribution, ERP 6.0 EhP6  https://it-pruefungen.de/C_TSCM62_66.htm

QUESTION: 3

How does SAP make new functions of the SAP ERP system available to the customer?

A. Via enhancement packages
B. Via Support Packages
C. Via best practices
D. Via add-ons

Answer: A

QUESTION: 4

In which of the following master records can partial delivery agreements be stored?(Choose two)

A. In the material master record
B. In the customer master record
C. In the customer material info record
D. In the condition master record

Answer: B,C

C_TSCM62_66 Prüfungsfragen SAP Certified Application Associate – Sales and Distribution, ERP 6.0 EhP6 www.it-pruefungen.de

QUESTION: 5

You are asked to set the system in such a way that it can automatically search for available quotations for customers when sales order items are entered.

What do you have to do to make this happen?

A. Set the quotation messages function in the quotation sales document type.
B. Set the completion rule in the item category for the quotation.
C. Set the quotation messages function in the sales order document type.
D. List the reference document number field in the incompleteness procedure for the sales order item category.

Answer: C

Prüfungsvorbereitung C_TSCM66_65

Prüfungsvorbereitung C_TSCM66_65, Studienmaterial C_TSCM66_65 deutsch SAP Certified Application Associate – Logistics Execution and Warehouse Management with SAP ERP 6.0 EHP5 www.it-pruefungen.de

Q1
You want to stage in consistent quantities independently of an order. Which material staging indicator would you use?

A. Indicator 4 (manual staging)
B. Indicator 3 (release order part)
C. Indicator 1 (pick part)
D. Indicator 2 (crate part)

Answer: D

Q2
What is the purpose of the storage bin field in the “Warehouse Mgmt 2″ view of the material master?

A. To identify the fixed storage bin for that material in the storage type
B. To identify the next empty storage bin for that material in the storage type
C. To identify the open storage bin for that material in the storage type
D. To identify the bulk storage bin for that material in the storage type

Answer: A

C_TSCM66_65 Prüfungsfragen, C_TSCM66_65 Examensfragen SAP Certified Application Associate – Logistics Execution and Warehouse Management with SAP ERP 6.0 EHP5 (ICND2 v3.0)  https://it-pruefungen.de/C_TSCM66_65.htm

Q3
How the determination of door and staging area happens during the outbound delivery?

(Choose three)

A. It also depends on the route schedule
B. Staging area determination can also take place at the delivery item level if the storage conditions are also taken into account
C. The determination can take place at the delivery header level depending on the goods recipient
D. The determination can take place at the delivery header level depending on the goods issuer

Answer: B,C,D

Q4
There are several documents created during the creation/posting a transaction in SAP.

Which of the following documents are not specific to Logistics Execution?

(Choose three)

A. Transfer order
B. Material document
C. Transfer requirements
D. Inbound delivery
E. Purchase Order
F. Sales order
G. Outbound delivery

Answer: B,E,F

C_TSCM66_65 IT-Prüfungen, C_TSCM66_65 zertifizierung SAP Certified Application Associate – Logistics Execution and Warehouse Management with SAP ERP 6.0 EHP5 www.it-pruefungen.de

Q5
What are the things to be taken into consideration for the implementation of RF solution?

(Choose three)

A. Recovery of connection in case of connection drop and reconnection
B. Customization and flow logic development in the production environment of SAP
C. Support for different connection types of RF terminals
D. Implementation of new devices with ease
E. Replacement of each screen with our own screen without change of processing logic

Answer: A,C,E

IT-Prüfung C_TSCM66_66

IT-Prüfung C_TSCM66_66 SAP Certified Application Associate – Logistics Execution and Warehouse Management with SAP ERP 6.0 EHP6 www.it-pruefungen.de

Q1
You want to stage in consistent quantities independently of an order. Which material staging indicator would you use?

A. Indicator 4 (manual staging)
B. Indicator 3 (release order part)
C. Indicator 1 (pick part)
D. Indicator 2 (crate part)

Answer: D

Q2
What is the purpose of the storage bin field in the “Warehouse Mgmt 2″ view of the material master?

A. To identify the fixed storage bin for that material in the storage type
B. To identify the next empty storage bin for that material in the storage type
C. To identify the open storage bin for that material in the storage type
D. To identify the bulk storage bin for that material in the storage type

Answer: A

Prüfungsvorbereitung Studienmaterial C_TSCM66_66 deutsch SAP Certified Application Associate – Logistics Execution and Warehouse Management with SAP ERP 6.0 EHP6  https://it-pruefungen.de/C_TSCM66_66.htm

Q3
How the determination of door and staging area happens during the outbound delivery?

(Choose three)

A. It also depends on the route schedule
B. Staging area determination can also take place at the delivery item level if the storage conditions are also taken into account
C. The determination can take place at the delivery header level depending on the goods recipient
D. The determination can take place at the delivery header level depending on the goods issuer

Answer: B,C,D

Q4
There are several documents created during the creation/posting a transaction in SAP.

Which of the following documents are not specific to Logistics Execution?

(Choose three)

A. Transfer order
B. Material document
C. Transfer requirements
D. Inbound delivery
E. Purchase Order
F. Sales order
G. Outbound delivery

Answer: B,E,F

Q5
What are the things to be taken into consideration for the implementation of RF solution?

(Choose three)

A. Recovery of connection in case of connection drop and reconnection
B. Customization and flow logic development in the production environment of SAP
C. Support for different connection types of RF terminals
D. Implementation of new devices with ease
E. Replacement of each screen with our own screen without change of processing logic

Answer: A,C,E

C_TSCM66_66 Prüfungsfragen, C_TSCM66_66 Examensfragen SAP Certified Application Associate – Logistics Execution and Warehouse Management with SAP ERP 6.0 EHP6 (ICND2 v3.0) www.it-pruefungen.de

Prüfungsvorbereitung auf C_TS4FI_1709

Prüfungsvorbereitung auf C_TS4FI_1709 PDF deutsch SAP Certified Application Associate : SAP S/4HANA for Financial Accounting Associates (SAP S/4HANA 1709) www.it-pruefungen.de

1. Which of the following steps are parts of the process of configuring the payment program? Choose the correct answers.

A. Configure the paying company codes
B. Configure the payment methods for each company code
C. Configure the house banks
D. Configure the G/L account field status for document entry

Answer: A,B,C

2. Which of the following are possible reasons that an invoice would not be paid? Choose the correct answers.

A. The invoice has a debit balance.
B. An invalid house bank is selected.
C. The discount period has expired.
D. The payment amount is less than the minimum amount specified for a payment.

Answer: A,B,D

C_TS4FI_1709 Prüfungsfragen, C_TS4FI_1709 Examensfragen SAP Certified Application Associate : SAP S/4HANA for Financial Accounting Associates (SAP S/4HANA 1709) (ICND2 v3.0)  https://it-pruefungen.de/C_TS4FI_1709.htm

3. Which of the following activities does the system perform during the payment run? Choose the correct answers.

A. The system exports a list of documents to be paid.
B. The system makes postings to the G/L and AP/AR subledgers.
C. The system clears open items.
D. The system supplies the print programs with necessary data.

Answer: B,C,D

4. There are four dunning program steps that can be performed during the automatic dunning procedure as follows: Arrange these steps into the correct sequence.

A. Maintain the parameters.
B. Schedule the dunning run.
C. Change the dunning proposal.
D. Start the dunning printout.

Answer: A,B,C,D

5. Which of the following objects are relevant to the dunning program configuration? Choose the correct answers.

A. Dunning levels
B. Expenses or charges
C. Minimum amounts
D. Bank selection

Answer: A, B, C