QUESTION NO: 1
What features related to process orders can be used to fulfill Good Manufacturing Practices (GMP) requirements? (Choose three)
A. Availability check
B. Digital signature
C. Resource selection
D. Electronic batch record
E. Approved master recipes
Answer: B,D,E
QUESTION NO: 2
Which of the following statements about consumption are correct? (Choose two)
A. Consumption takes place on the material level between the planned independent requirements and the planned orders.
B. Consumption parameters (consumption mode and consumption interval) can be set in the material master or in the MRP group.
C. Consumption is restructured with the planning run.
D. Consumption can take place between order reservations and planned independent
requirements, depending on the strategy.
Answer: B,D
QUESTION NO: 3
Where can you define the valid receivers for production order costs?
A. In the valuation variant
B. In the production scheduling profile
C. In the settlement profile
D. In the costing variant
Answer: C
Prüfungsvorbereitung C_TSCM42_65 Studienmaterial deutsch SAP Certified Application Associate – Production – Planning & Manufacturing with SAP ERP 6.0 EHP5 https://www.it-pruefungen.de/C_TSCM42_65.htm
QUESTION NO: 4
When analyzing the SAP ECC order report for a planned order for a finished product, you discover that one of the assemblies will not be available in time for the scheduled final assembly because of automatic forward scheduling.
Which planning procedure do you use to create a feasible production plan from a requirements planning perspective?
A. Interactive single-item planning for the delayed assembly
B. Multi-level single-item planning with the “simulation mode” option
C. Total planning online
D. Multi-level single-item planning with the “display material list” option
Answer: B
QUESTION NO: 5
What does SAP ERP mean?
A. SAP ERP is a planning system in which extended planning processes can be mapped.
B. SAP ERP is a system hardware that includes modules for purchasing, sales and distribution, materials management, production and so on.
C. SAP ERP is a technological platform, on the basis of which customer-specific extensions can be imported.
D. SAP ERP is an application that an enterprise can use to manage its business processes efficiently.
Answer: D
IT-Prüfungen C_TSCM42_65 SAP Certified Application Associate – Production – Planning & Manufacturing with SAP ERP 6.0 EHP5 www.it-pruefungen.de
QUESTION NO: 6
Which functions can be triggered before releasing a production order? (Choose three)
A. Confirmation
B. Selection of a routing
C. Scheduling
D. Stock determination
E. Selection of a BOM
Answer: B,C,E